Schedules
| Design Phases | Fall 06 - Fall 07 |
| Permitting & Bidding | Fall 07 - Winter 08 |
| Excavation starts on current site | Mid August 07 |
| Ground Breaking Ceremony | October 26, 07 |
| Remodeling | Starts Fall 07 |
| Construction (New Building) | Winter 08 - Summer 09 |
| Completion / Move in (New Building) | Summer 09 |
Moves - COE Project July 25, 2007
| General Phasing Time Line and Moving Schedule. |
| Pre-Phase: Aug 07 - June 09 (Ed Annex) Moves to occur 6/07-8/07 |
| Phase 1: Oct 07 - June 08 (East Wing and ED Addition-East End) Moves occur 7/07-10/07 |
| Phase 2: Jan 08 - June 08 (ED Addition-West End) Moves occur Winter Break '07 |
| Phase 3: Apr. 08 - Jan 09 (UNI HIGH South End) Moves occur Spring Break '08 |
| Phase 4: July 08 - Jan 09 (UNI HIGH-North End) Moves occur 6/08 - 7/08 |
| Phase 5: July 08 - Jan 09 (CSB) Moves varies. |
| Phase 6: Jan 09 - June 09 (SW CORNER SITE WORK) |
| Completion: June 09 (NEW BUILDING COMPLETED) |
Resources & Final Program $48 Million
New Construction – 65,000 GSF, $22.6m
Renovations - $5.5m
Campus Improvements - $1.9m
Parking - $4.1m
200 spaces in structured parking
175 surface parking spaces
Total Direct Construction Costs: $34.1
Works of Art - 341,000
Building equipment and furnishings - 2.5m
Design, management, landscaping, networking, fees, permits, misc - 11.2m
Total Project Costs: 48.1m