UO College of Education Building Project

Building Project Plans

Buildig drawingFor Current Building Plans Conact Your Business Manager

The building plans on this page are basically correct but do not show all the ongoing changes . For up-to-date plans please contact your department business manager or Elaine Jones at ejones@uoregon.edu.

Schedules

Design Phases Fall 06 - Fall 07
Permitting & Bidding Fall 07 - Winter 08
Excavation starts on current site Mid August 07
Ground Breaking Ceremony October 26, 07
Remodeling Starts Fall 07
Construction (New Building) Winter 08 - Summer 09
Completion / Move in (New Building) Summer 09

Moves - COE Project July 25, 2007

General Phasing Time Line and Moving Schedule.
Pre-Phase:  Aug 07 - June 09 (Ed Annex) Moves to occur 6/07-8/07
Phase 1:  Oct 07 - June 08 (East Wing and ED Addition-East End) Moves occur 7/07-10/07
Phase 2:  Jan 08 - June 08 (ED Addition-West End) Moves occur Winter Break '07
Phase 3:  Apr. 08 - Jan 09 (UNI HIGH South End) Moves occur Spring Break '08
Phase 4:  July 08 - Jan 09 (UNI HIGH-North End) Moves occur 6/08 - 7/08
Phase 5:  July 08 - Jan 09 (CSB) Moves varies.
Phase 6:  Jan 09 - June 09 (SW CORNER SITE WORK)
Completion:  June 09 (NEW BUILDING COMPLETED)


Resources & Final Program $48 Million

New Construction – 65,000 GSF, $22.6m
Renovations - $5.5m
Campus Improvements - $1.9m
Parking - $4.1m
200 spaces in structured parking
175 surface parking spaces
Total Direct Construction Costs: $34.1

Works of Art - 341,000
Building equipment and furnishings - 2.5m
Design, management, landscaping, networking, fees, permits, misc - 11.2m
Total Project Costs: 48.1m

 

Prepared by Terry Kneen tkneen@uoregon.edu May 13, 2008